*** Welcome to piglix ***

Yusufeli Dam

Yusufeli Dam
Yusufeli dam.jpg
A view of Yusufeli
Yusufeli Dam is located in Turkey
Yusufeli Dam
Location of Yusufeli Dam in Turkey
Official name Yusufeli Baraji
Country Turkey
Location Yusufeli, Artvin Province
Coordinates 40°49′13″N 41°39′41″E / 40.82028°N 41.66139°E / 40.82028; 41.66139Coordinates: 40°49′13″N 41°39′41″E / 40.82028°N 41.66139°E / 40.82028; 41.66139
Status Under construction
Construction began February 26, 2013
Opening date May 2018 est.
Construction cost Turkish lira symbol 8x10px.png487 million (approx. US$270 million)
Owner(s) State Hydraulic Works
Dam and spillways
Type of dam Arch, double-curvature
Impounds Çoruh River
Height 270 m (886 ft)
Length 490 m (1,608 ft)
Width (crest) 15 m (49 ft)
Dam volume 2,900,000 m3 (102,412,533 cu ft)
Spillway type Service, controlled chute
Spillway capacity 8,000 m3/s (282,517 cu ft/s)
Reservoir
Creates Yusufeli Reservoir
Total capacity 2,130,000,000 m3 (1,726,819 acre·ft)
Surface area 33 km2 (13 sq mi)
Power station
Turbines 3 x 180 MW Francis turbines
Installed capacity 540 MW
Annual generation 1,705 GWh (est.)

The Yusufeli Dam is an arch dam under construction on the Çoruh River near Yusufeli in Artvin Province within the eastern Black Sea region of Turkey. The Yusufeli Dam will be the second largest dam within the larger Çoruh River Development Plan, which plans to build 13 dams, of which two are operational and another two are under construction. The dam's main purpose is hydroelectric power production and it will support a 540 MW power station. The dam is controversial because of its projected impact on the biodiversity within its reservoir area along with the relocation of locals.

On February 26, 2013, the foundation stone was laid in a ceremony attended by Minister of Forestry and Waterworks Veysel Eroğlu and Minister of Labor and Social Security Faruk Çelik. It is expected that the construction of the dam will cost Turkish lira symbol 8x10px.png487 million (approx. US$270 million). The dam's opening date is set to May 29, 2018. When completed, Yusufeli Dam will be Turkey's highest.

The first studies on the Yusufeli Dam were carried out in the 1970s and it was included in the Coruh River Hydropower Development Master Plan in 1982. The feasibility report was completed in 1986 and the project was added to the national plan in 1997.

Situated 70 km (43 mi) southwest of Artvin, the Yusufeli will be a double-curvature arch dam with a height of 270 m (886 ft) from its foundation and 223 m (732 ft) from the river's thalweg (lowest point of river bed). It will have a crest length of 490 m (1,608 ft) and crest width of 15 m (49 ft) while being composed of 2,900,000 m3 (102,412,533 cu ft) of concrete.

The dam's crest will sit at an altitude of 715 m (2,346 ft) above sea level while the normal operating level of its reservoir will be 710 m (2,329 ft), maximum will be 712 m (2,336 ft) and the minimum 670 m (2,198 ft). The reservoir surface area of 33 km2 (13 sq mi) will have a total storage capacity of 2,130,000,000 m3 (1,726,819 acre·ft) and an active or "useful" storage of 1,080,000,000 m3 (875,570 acre·ft). The dam's spillway will be a service controlled chute type with a maximum discharge capacity of 8,000 m3/s (282,517 cu ft/s).


...
Wikipedia

...