Xiluodu Dam | |
---|---|
Location of Xiluodu Dam in China
|
|
Official name | 溪洛渡大坝 |
Location | Xiluodu Town, Yongshan County, Yunnan/Leibo County Sichuan, China |
Coordinates | 28°15′35.46″N 103°38′58.20″E / 28.2598500°N 103.6495000°ECoordinates: 28°15′35.46″N 103°38′58.20″E / 28.2598500°N 103.6495000°E |
Construction began | December 2005 |
Opening date | July 2013 |
Construction cost | US$6.2 billion |
Dam and spillways | |
Type of dam | Double-curvature arch, concrete |
Impounds | Jinsha River |
Height | 285.5 m (937 ft) |
Length | 700 m (2,300 ft) |
Elevation at crest | 610 m (2,000 ft) |
Spillway type | 7 × crest floodgates, 7 × orifices, 4 × tunnels |
Spillway capacity | 32,278 m3/s (1,139,900 cu ft/s) |
Reservoir | |
Creates | Xiluodu Reservoir |
Total capacity | 12,670,000,000 cubic metres (10,270,000 acre·ft) |
Active capacity | 6,460,000,000 cubic metres (5,240,000 acre·ft) |
Catchment area | 454,400 km2 (175,400 sq mi) |
Normal elevation | 600 m (2,000 ft) |
Power station | |
Name | Xiluodu Hydropower Station |
Operator(s) | China Yangtze Power |
Commission date | 2013–2014 |
Turbines | 18 × 770 MW Francis-type |
Installed capacity | 13,860 MW |
Annual generation | 55.2 TWh (2015) |
The Xiluodu Dam (simplified Chinese: 溪洛渡大坝; traditional Chinese: 溪洛渡大壩; pinyin: Xīluòdù Dàbà) is an arch dam on the Jinsha River, i.e. the upper course of the Yangtze in China. It is located near the town of Xiluodu in Yongshan County of Yunnan Province but the dam straddles into Leibo County of Sichuan Province on the opposite side of the river. The primary purpose of the dam is hydroelectric power generation and its power station has an installed capacity of 13,860 MW. Additionally, the dam provides for flood control, silt control and its regulated water releases are intended to improve navigation downstream. Construction on the dam and power station began in 2005 and the first generator was commissioned in 2013, the last in 2014. It is operated by China Yangtze Power and is currently the third-largest power station with the fourth-tallest dam in the world.
Preliminary construction (roads, bridges, tunnels) for the dam began in 2003 and work on main structures officially commenced on 26 December 2005. In November 2007, the Jinsha was successfully diverted around the construction site, allowing the dam to be built. Concrete pouring began in 2008. The reservoir was impounded in May 2013 and the first of 18×770 MW Francis turbine-generators was commissioned on 15 July 2013. The fourteenth generator was commissioned in April 2014. The eighteenth and final generator was commissioned on 30 June 2014.