West African Gas Pipeline

West African Gas Pipeline
Location
Country Nigeria, Benin, Togo, Ghana
General direction east–west
From Itoki terminal, Lagos, Nigeria
To Takoradi, Ghana
General information
Type natural gas
Owner West African Gas Pipeline Company Limited
Partners Chevron, Nigerian National Petroleum Corporation, Royal Dutch Shell, Volta River Authority, Société Togolaise de Gaz, Société Beninoise de Gaz
Operator Chevron
Contractors Willbros
Commissioned 2006
Technical information
Length 678 km (421 mi)
Maximum discharge 5 billion cubic meter per year
Diameter 20 in (508 mm)

The West African Gas Pipeline (WAGP) is a natural gas pipeline to supply gas from Nigeria's Escravos region of Niger Delta area to Benin, Togo and Ghana. It is the first regional natural gas transmission system in sub-Saharan Africa.

The project began in 1982, when the Economic Community of West African States (ECOWAS) proposed the development of a natural gas pipeline throughout West Africa. In 1991 a feasibility report conducted by the World Bank on supplying Nigerian gas on West African markets deemed that a project was commercially viable.

In September 1995, the governments of four African countries signed a Heads of State Agreement. The feasibility study was carried out in 1999. On 11 August 1999, a Memorandum of Understanding was signed by participating countries in Cotonou, Benin. In February 2000, an Inter-Governmental Agreement was signed. The WAGP implementation agreement was signed in 2003. Groundbreaking ceremonies for the project were held at Sekondi-Takoradi, Ghana, on 3 December 2004. Construction began in 2005.

The offshore pipeline was completed in December 2006 and was scheduled to start operating on 23 December 2007 but was delayed after leaks were detected in supply pipelines in Nigeria. The second delivery deadline was scheduled on 13 February 2008, but regular deliveries were delayed again, when one of the contractors of Willbros was shot and killed in Nigeria by armed robbers.

Gas deliveries were expected by the end of 2009 after commissioning regulating and metering stations in Takoradi and Tema, Ghana, Lagos Beach, Nigeria, Cotonou, Benin, and Lomé, Togo in May 2008. However, deliveries were postponed again due to an irregular amount of moisture found inside the onshore gas pipeline.

The pipeline consists three sections with a total length of 678 kilometres (421 mi). The 569 kilometres (354 mi) long offshore section starts at starts the Itoki terminal in southeastern Nigeria and runs through the waters of Benin, Togo and Ghana parallel to the coastline, approximately 15 kilometres (9.3 mi) to 20 kilometres (12 mi) offshore in water depths of between 30 metres (98 ft) and 75 metres (246 ft). The Nigerian onshore section of the pipeline connects the offshore section compressor station at Lagos Beach with the Chevron-owned Escravos–Lagos Pipeline System, operational since 1989. It is possible that later the WAGP will be extended to Côte d'Ivoire and in longer term even to Senegal.


...