T.F. Green Airport (MBTA station)

T. F. GREEN AIRPORT Pictograms-nps-airport.svg
T.F. Green Platform.JPG
T.F. Green Airport station platform, facing outbound
Location 700 Jefferson Boulevard
Warwick, Rhode Island
Coordinates 41°43′39″N 71°26′30″W / 41.7275°N 71.4417°W / 41.7275; -71.4417Coordinates: 41°43′39″N 71°26′30″W / 41.7275°N 71.4417°W / 41.7275; -71.4417
Owned by State of Rhode Island
Line(s)
Platforms 1 side platform
Tracks 3
Connections RIPTA: 1, 8, 14, 20
Construction
Parking 650 spaces ($6.75 daily fee)
24 accessible spaces
Bicycle facilities racks available
Disabled access Yes
Other information
Fare zone 9
History
Opened December 6, 2010
Electrified Amtrak tracks but not MBTA station siding
Traffic
Passengers (2017) 414 (weekday inbound average)
Services
Preceding station   MBTA.svg MBTA   Following station
Terminus
Providence/Stoughton Line
Terminus Providence/Stoughton Line
Limited service for Patriots games only
toward Foxboro
  Proposed services  
Preceding station   BSicon LOGO Amtrak2.svg Amtrak   Following station
Northeast Regional

T. F. Green Airport is a train station and intermodal facility in Warwick, Rhode Island on the Northeast Corridor, adjacent to T. F. Green Airport. It extends the MBTA Commuter Rail Providence/Stoughton Line from Boston, which previously only went as far as the Providence train station. The station was completed in October 2010 and MBTA service began on December 6, 2010. On November 14, 2011, service expanded to 10 weekday trains in each direction. Trips to and from Boston's South Station take 75 to 90 minutes.

The station's primary purpose is to serve local commuters to Providence and Boston, but it will also bring passengers and employees to and from the airport. The station also makes it possible to move between T.F. Green and Logan International Airport in about two hours via subway and commuter rail. Amtrak trains cannot and do not serve the station because the track that serves the single platform is not electrified. Funding was not provided for the necessary track and electrical work, although long-range plans call for this infrastructure to be provided.

A state study of rail corridors was completed in 1994 and the Northeast Corridor was designated as the highest-priority line for commuter service to Providence. An addendum in 1995 projected daily ridership from a Warwick station to be 454 in 2000 and 529 in 2020. An operations plan was released in 2001, and environmental assessment was completed in 2003.

The station's ceremonial groundbreaking took place on July 17, 2006, but construction was delayed by negotiations with Amtrak over the agreement to allow the MBTA to run commuter trains on Amtrak-owned tracks. Site preparation began in September 2007 and construction began in late 2008 or early 2009. The station was originally scheduled to open in late 2010, and construction was completed on schedule, with the opening ceremony taking place on October 27, 2010.

On October 13, 2010, the MBTA and the Rhode Island Department of Transportation signed an agreement enabling MBTA operations to the station to begin on December 6, 2010, initially with 6 inbound and 5 outbound trains each weekday. This service consisted of three peak-hour trains in each direction between T.F. Green and South Station, plus several off-peak shuttles to/from Providence. This was despite earlier concerns that service could be delayed pending completion of the Wickford Junction station and the siding there used to allow trains to reverse directions. However, the siding at T.F. Green was deemed sufficient for operations. In November 2011, service was increased significantly, with mid-day service and more rush hour trains. The line was extended 10 miles past T.F. Green with the opening of Wickford Junction station in April 2012.


...