Port Qasim Power Project
Pakistan Port Qasim Power Project is located in Sindh
Pakistan Port Qasim Power Project
Location of the Port Qasim Power Project in Sindh province.
Country Pakistan
Location Port Qasim, Sindh
Coordinates 24°47′07″N 67°22′10″E / 24.7854°N 67.3695°E / 24.7854; 67.3695Coordinates: 24°47′07″N 67°22′10″E / 24.7854°N 67.3695°E / 24.7854; 67.3695
Status Under Construction
Construction began May 2015
Commission date 2018 (expected)
Construction cost $2.09 billion USD
Owner(s) Port Qasim Energy Holding and Sinohydro Resources Limited
Thermal power station
Primary fuel Bituminous coal
Power generation
Nameplate capacity 1,320 MW

The 1,320 megawatt Pakistan Port Qasim Power Project comprises two 660 megawatt supercritical coal power plants which have been under construction since May 2015 as part of the China–Pakistan Economic Corridor. The $2.09 billion project will be located on 204 acres at Port Qasim, 37 kilometers east of Karachi in Sindh Province. The project is to be part of a group of 14 energy projects which fall under the fast-tracked "Early Harvest" program of the $46 billion China Pakistan Economic Corridor project.

The plants will be built on a "Build-Own-Operate" basis, and is to be constructed and operated by the Port Qasim Energy Holding, a firm jointly financed by Qatar's Al-Mirqab Capital and China's Power Construction Corporation, a subsidiary of Sinohydro Resources Limited.

The project will consist not only of the power plants themselves, but also will include the construction of a jetty for exclusive use of the power plant for coal importation. When both 660 MW plants are complete, the estimated annual coal consumption for the plants will be 4.66 million tons, and enough annual power for an estimated 3-4 million households will be generated.

The plants will each consist of one boiler, steam turbine and generator, and will be fueled by sub-bituminous coal which will be offloaded at the project's coal jetty. Electricity will be connected to the electric grid network K-Electric via a 500 kilovolt AC transmission line. The plant's gross efficiency will be equal to or greater than 41%, while the net efficiency will be equal to or greater than 38%.

Additionally, living quarters for up to 700 full-time workers will be constructed at the site, with additional temporary housing facilities for 11,000 construction workers divided into a unit for 2,000 Chinese construction workers, and another unit for 9,000 Pakistani construction workers, with all construction materials for living quarters to be provided by Chinese manufacturers.

Most of the coal used for the power plant will be imported from Indonesia, with South Africa and Australia identified as suitable supplemental suppliers. Indonesia is identified as a primary source for its high quality coal, reliable production, and short transit times to Pakistan.


...