New Works Programme


The "New Works Programme, 1935–1940" was the major investment programme delivered by the London Passenger Transport Board (LPTB), commonly known as London Transport, which had been created in 1933 to coordinate underground train, tram, trolleybus and bus services in the capital and the surrounding areas. The programme was to develop many aspects of the public transport services run by the LPTB and the suburban rail services of the Great Western Railway (GWR) and London and North Eastern Railway (LNER). The investment was largely backed by government assistance as well as by the issuing of financial bonds and was estimated to cost £42,286,000 in 1936(approximately £2.59 billion today).

The Programme saw major reconstructions of many central area Underground stations, with escalators being installed to replace lifts; extensions of several tube lines; and connection to and electrification of a number of suburban lines. These included:

On the city's roads, the Programme was to see the large-scale abandonment of trams and their replacement by trolleybuses, creating the world's largest trolleybus system at that date.

Substantial and rapid progress was made on the network across the capital before the advent of World War II delayed, then prevented its completion. The Central line tunnel relining works were completed in 1938 and the replacement of the line's power supply was completed in 1940. The Bakerloo line service to Stanmore started on 20 November 1939. The 1938 tube stock came into operation as intended although the extensions they were built for were not completed at once.

Progress on the Northern line works enabled the extension from Archway to come into service as far as East Finchley on 3 July 1939 (excluding Highgate station), where interchanges were made with the LNER services. Underground services to High Barnet commenced on 14 April 1940. Highgate station came into use on 19 January 1941 and services started operating on the branch to Mill Hill East on 18 May 1941. This latter section was finished, exceptionally, to serve Inglis Barracks. The outstanding electrification works on the remainder of the LNER's branch from Finsbury Park to Highgate, from Highgate to Alexandra Palace and from Mill Hill East to Edgware were halted. Works on the extension beyond Edgware were also stopped, although the construction of the new tube depot at Aldenham was completed and the buildings were used to construct Halifax bomber aircraft for the RAF. Other parts of the land purchased for the Bushey Heath extension were farmed during the war to provide food for London Transport canteens.


...