*** Welcome to piglix ***

Kashiwazaki-Kariwa Nuclear Power Plant

Kashiwazaki-Kariwa Nuclear Power Plant
Kashiwazaki-Kariwa cropped.jpg
Aerial view. The breakwaters where seawater is taken from in order to cool waste heat water, can be seen clearly.
Kashiwazaki-Kariwa Nuclear Power Plant is located in Japan
Kashiwazaki-Kariwa Nuclear Power Plant
Location of Kashiwazaki-Kariwa Nuclear Power Plant in Japan
Country Japan
Coordinates 37°25.7′N 138°36.1′E / 37.4283°N 138.6017°E / 37.4283; 138.6017Coordinates: 37°25.7′N 138°36.1′E / 37.4283°N 138.6017°E / 37.4283; 138.6017
Construction began June 5, 1980 (1980-06-05)
Commission date September 18, 1985 (1985-09-18)
Operator(s) Tokyo Electric Power Company
Nuclear power station
Cooling source Sea of Japan
Cooling towers no
Power generation
Units operational 5 × 1,067 MW
2 × 1,315 MW
Nameplate capacity 7,965 MW
Capacity factor 0%
2012 generation 0 GW·h

The Kashiwazaki-Kariwa Nuclear Power Plant (柏崎刈羽原子力発電所 Kashiwazaki-Kariwa genshiryoku-hatsudensho?, Kashiwazaki-Kariwa NPP) is a large, modern (housing the world's first ABWR) nuclear power plant on a 4.2-square-kilometer (1,038 acres) site including land in the towns of Kashiwazaki and Kariwa in Niigata Prefecture, Japan on the coast of the Sea of Japan, from where it gets cooling water. The plant is owned and operated by Tokyo Electric Power Company (TEPCO).

It was the largest nuclear generating station in the world by net electrical power rating.

It was approximately 19 km (12 mi) from the epicenter of the second strongest earthquake to ever occur at a nuclear plant, the Mw 6.6 July 2007 Chūetsu offshore earthquake. This shook the plant beyond design basis and initiated an extended shutdown for inspection, which indicated that greater earthquake-proofing was needed before operation could be resumed. The plant was completely shut down for 21 months following the earthquake. Unit 7 was restarted after seismic upgrades on May 9, 2009, followed later by units 1, 5, and 6. (Units 2, 3, 4 were not restarted).

After the April 2011 earthquake, all restarted units were shut down and safety improvements are being carried out. As of December 2016 no units are restarted and no units are expected to restart sooner than in 2017.


...
Wikipedia

...