Bukhara–Tashkent–Bishkek–Almaty pipeline

Bukhara–Tashkent–Bishkek–Almaty pipeline
Location of Bukhara–Tashkent–Bishkek–Almaty pipeline
Location of Bukhara–Tashkent–Bishkek–Almaty pipeline
Location
Country Uzbekistan, Kyrgyzstan, Kazakhstan
General direction west–east
From Bukhara, Uzbekistan
Passes through Tashkent, Shymkent, Taraz, Bishkek
To Almaty, Kazakhstan
General information
Type natural gas
Partners Uzbekneftegas, Kyrgyzgas, KazMunayGas
Operator Uzbekneftegas, KyrKazGas, KazTransGas
Commissioned 1971
Technical information
Maximum discharge 22 billion cubic meters

The Bukhara–Tashkent–Bishkek–Almaty pipeline is a Uzbekistan's main natural gas export pipeline.

Construction of the pipeline started in 1967. In 1968, the pipeline reached to Tashkent, in 1970 to Bishkek (then Frunze) and in 1971 to Almaty.

The diameter of the pipeline is 1,020 millimetres (40 in) and the annual capacity of the pipeline is almost 22 billion cubic meter (bcm) of natural gas. The Bukhara–Tashkent–Bishkek–Almaty pipeline is the main source of gas supply for Kyrgyzstan and southern part of Kazakhstan. It is possible that the pipeline will be connected with the planned Central Asia-China gas pipeline.

The Kazakhstan section of pipeline is operated by KazTransGas, a wholly owned subsidiary of KazMunayGas. The Kyrgyzstan section of pipe line is operated by KyrKazGas, the joint venture of KazTransGas and Kyrgyzgas.

The technical condition of the pipeline is alarming, particularly in Kyrgyzstan. Therefore, there are plans for construction of a second trunk gas pipeline and renovation of the existing pipeline.


...
Wikipedia

...