*** Welcome to piglix ***

Winchester Center station

WINCHESTER CENTER
Winchester Center platforms, January 2013.JPG
Winchester Center station in January 2013
Location 29 Waterfield Road
Winchester, Massachusetts 01890
Coordinates 42°27′06″N 71°08′16″W / 42.4516°N 71.1378°W / 42.4516; -71.1378Coordinates: 42°27′06″N 71°08′16″W / 42.4516°N 71.1378°W / 42.4516; -71.1378
Line(s)
Platforms 2 side platforms
Tracks 2
Construction
Parking 237 spaces (town permit required)
2 accessible spaces
Bicycle facilities 27 spaces
Other information
Fare zone 1
Traffic
Passengers (2013) 789 (weekday inbound average)
Services
Preceding station   MBTA.svg MBTA   Following station
Lowell Line
toward Lowell
Haverhill Line
limited service
toward Haverhill
  Former services  
Lowell Line
Woburn Branch
Closed 1981

Winchester Center station is an MBTA Commuter Rail station in Winchester, Massachusetts. It serves all Lowell Line trains as well as a limited number of Haverhill Line trains which run via the Wildcat Branch. It is located on a viaduct in downtown Winchester. Winchester Center station is not handicapped accessible, but the MBTA plans to renovate the station and add accessible high-level platforms beginning in 2017.

The Boston and Lowell Railroad opened between its namesake cities in 1835; local stops including Winchester were added soon after. By the 1840s, service on the line was suitable for commuting to Boston.

In 1955, the Boston and Maine Railroad began a project to raise the tracks of the New Hampshire Main and the southern end of the Woburn Branch for a mile through Winchester, eliminating troublesome grade crossings in the downtown area. Boxy two-story brick stations were opened at Wedgemere and Winchester Center in 1957.

Until 1981, the Woburn Branch diverged from the main line just north of the Winchester Center platforms. A short stub is still in place.

Winchester Center station has not been substantially renovated since the viaduct was completed in 1957. In September 2008, the MBTA approved $1.4 million in platform and ramps repairs, as well as electrical and lighting work, at the station. The work was completed in 2010; the MBTA intended to renovate the station before the 5-year life of the platform patches was reached.

On July 7, 2015, the Winchester Department of Public Works discovered a hole in the inbound platform, which prompted the closure of the northern 500 feet (150 m) of the platform and one ramp due to concrete deterioration. One ramp and the remaining section of the platform remained open for service. The MBTA planned to make temporary repairs before the end of the year.

As of 2016, the MBTA is in the process of designing renovations to the station which will repair water damage and make it handicapped accessible. The station design was advanced to 15% in December 2011; Jacobs Engineering was then chosen as the contractor for final design in June 2012. The 15% design level was reached in early 2016, with 30% design under way. The rebuilt station will have 724-foot (221 m)-long high-level platforms; although shorter than the 800-foot (240 m) MBTA standard, they will still be able to platform 9 cars. A gauntlet track may be installed to allow Pan Am Railways freight trains to pass. A new interlocking may be built south of the station, which will allow greater flexibility during construction and allow the retirement of the former Woburn Branch interlocking north of the station after completion. Although early designs only had ramps for accessibility, the 15% design added a pair of elevators for easier access. Design of the station is expected to be completed by the end of 2016, with the $25.8 million construction beginning in 2017. By October 2016, bidding was expected to begin in December 2016.


...
Wikipedia

...