Temelín Nuclear Power Station | |
---|---|
Country | Czech Republic |
Coordinates | 49°10′48″N 14°22′34″E / 49.18000°N 14.37611°ECoordinates: 49°10′48″N 14°22′34″E / 49.18000°N 14.37611°E |
Status | Operational |
Construction began | 1981 |
Commission date | 10 June 2002 |
Construction cost | 98.6 billion CZK |
Operator(s) | ČEZ, a. s. |
Nuclear power station | |
Reactor type | VVER 1000/320 PWRs |
Power generation | |
Units operational | 2 x 1003 MWe (net), 1056 MWe (gross) |
Average generation | 15,302 GWh |
Website Company Website |
Temelín Nuclear Power Station (Czech: Jaderná elektrárna Temelín, abbreviation JETE) is located near Temelín, a small village in the Czech Republic. Temelín NPP is owned by ČEZ Group, which employs 1000 workers at this site. The adjacent castle Vysoký Hrádek serves as an information centre.
In spring 2003, the Temelín Nuclear Power Plant, with its 2,000 MW of installed capacity, became the largest power resource in the Czech Republic.
Planning began in the late 1970s and the final project was submitted in 1985. Construction of four operating units began in 1987. The project was expected to be completed in 1991 with estimated building costs of 35 billion Kčs. Six villages were demolished by the then-Communist government to make way for the power station.
After the Velvet revolution in 1990 the Czechoslovakian government decided to cease construction of the third and fourth reactors. Work continued on the first two reactors; in the 1990s alterations to the original design were made by Westinghouse in conjunction with SUJB and the IAEA to bring reliability and safety levels into conformance with Western European standards. The standards audit was carried out by Halliburton NUS. As part of the alterations information and control systems were added, electrical modifications carried out, and cabling, reactor core and fuel elements were replaced. In 1993 the Czech government decided to complete the plant in the face of delays and cost overruns, with expected completion at the time estimated for 1997. In 1994 an opinion poll reported that 68% of Czech citizens were in favor of nuclear power development.
In 1998 construction still was not completed and costs reached 71 CZK billion. The Czech government again reconsidered completion of the plant. In 1999 the decision was made to continue, hoping for an expected completion in 2000 with a maximum cost of 98.6 CZK billion. The project was controversial; national and international (mainly Austrian) opposition was stronger than in the early 1990s. In a 1999 opinion poll 47% of Czech citizens were in favor and 53% against nuclear power development.