Rand railway line

Rand Branch Line
km Station
53 Rand
46 Ferndale
37 Urangeline East
26 Pleasant Hills
18 Munyabla
14 Ryan
0 Main South line at Henty

The Rand railway line is a closed railway line in New South Wales, Australia. The line ran for 53km south-west to the town of Rand from the Main South railway line at Henty.

In 1908, a petition was handed to the Minister for Public Works requesting the construction of a railway from Yerong Creek to Daysdale, via Pleasant Hills. By October that year, a survey had been conducted and it was recommended that a line from Henty was preferable.

A further deputation was made to the Minister on 10 November 1910 and he suggested that an unballasted line could be acceptable to Government. Eleven months later, on 25 October 1911, the Minister for Public Works recommended that the line be referred to the Parliamentary Standing Committee on Public Works. The enquiry opened on 16 November.

Following many hearings at locations throughout the area, the Committee returned to Sydney and passed the resolution that the line be built from Henty towards Daysdale, but be carried out to Billabong Creek, the site of the future township of Rand. On 29 November 1916 the requisite Act was signed by the Governor.

The Public Works Department commenced construction in March, 1918. The rails for the line were being rolled at Newcastle, but supply was short and delays ensued. By May 1919, the line had reached Pleasant Hills and goods were carried over the line. Twelve months later the line reached Rand.

In 1918 there was a proposal to extend the line from Rand to Ringwood. The matter was investigated by the Parliamentary Standing Committee of Public Works, but it was rejected in 1922.

The line was available for traffic from 17 May 1920. It was an unfenced, "Pioneer" line. Stations were established at Ryan, Munyabla, Pleasant Hills, Urangeline, Ferndale and Rand. All intermediate stations were unattended.

The Official Opening took place on 16 October 1920. There was a ribbon cutting ceremony at Rand and a banquet in the Pleasant Hills Literary Institute.

At the commencement, the service on the line was a Mixed Train (comprising goods vehicles and a passenger carriage) on Mondays, Wednesdays and Fridays. This was probably hauled by a Z12-class locomotive. It made the return journey the following day. From January 1922, the train returned to Henty on the same day as the outward journey.


...