*** Welcome to piglix ***

NordBalt

Map of NordBalt.jpg
Country Lithuania, Sweden
Coordinates 55°40′54″N 21°15′24″E / 55.68167°N 21.25667°E / 55.68167; 21.25667 (Klaipėda substation)
56°46′4″N 15°51′15″E / 56.76778°N 15.85417°E / 56.76778; 15.85417 (Nybro substation)
General direction east–west
From Klaipėda
Passes through Baltic Sea
To Nybro
Partners Litgrid
Svenska kraftnät
Manufacturer of conductor/cable ABB
Manufacturer of substations ABB
Construction started 11 April 2014
Construction cost €552 million
Commissioned 14 December 2015
Type subsea cable
Type of current HVDC
Total length 450 km (280 mi)
Power rating 700 MW
AC voltage 330 kV
400 kV
DC voltage ±300 kV
No. of poles 2

NordBalt (also formerly known as SwedLit) is a submarine power cable between Klaipėda in Lithuania and Nybro in Sweden. The purpose of the cable is to facilitate the trading of power between the Baltic and Nordic electricity markets, and to increase the supply and energy security in both markets.

The project was originally suggested in 2004. Original project Swindlit was aimed at construction of the wind farm in the Baltic Sea and ensuring the electricity transmission to Sweden and Lithuania. The participants of this project were interested also in Kruonis Pumped Storage Plant as an accumulator of variable wind energy.

In August 2006, the Lithuanian and Swedish transmission grid operators Lietuvos Energija and Svenska kraftnät agreed to launch a feasibility study of a possible interconnector. In February 2007, Lietuvos Energija and Svenska Kraftnät signed an agreement with Swedish consulting company SWECO International on preparation of feasibility study. The study was completed in March 2008 with positive conclusions for the implementation of the project.

On 9 July 2009, Lietuvos Energija, Latvenergo and Svenska Kraftnät signed a memorandum of understanding on the NordBalt project. Invitation for pre-qualification for NordBalt converters' and cable procurement was launched in December 2009. The sea bottom survey was conducted by Marin Mätteknik by 13 December 2009. On 17 December 2010, Litgrid, a newly established transmission system operator of Lithuania who took the project over from Lietuvos Energija, and Svenska kraftnät, signed a €270 million contract with ABB according to which ABB manufactured the cable. According to another contract, signed on 20 December 2010, ABB supplied two converter stations.

In March 2013 the government of Lithuania approved construction plans for the coastal area. On 18 April 2013 the Swedish government gave its final approval of the construction of a power cable. Cable laying started on 11 April 2014. It was laid by using C/S Lewek Connector. The cable laying was disrupted several times by the Russian Navy within the Exclusive Economic Zone of Lithuania causing the Lithuanian prime minister to summon the Russian ambassador and protest against Russia's violation of the United Nation's Convention on the Law of the Sea (UNCLOS). On 9 June 2015, the cable laying works were completed.


...
Wikipedia

...