Montague Street Tunnel

Montague Street Tunnel
Montague Tube vc.jpg
Overview
Line BMT Fourth Avenue Line (N R trains)
Location East River between Manhattan, New York and Brooklyn, New York
Coordinates 40°41′53″N 74°00′20″W / 40.69806°N 74.00556°W / 40.69806; -74.00556Coordinates: 40°41′53″N 74°00′20″W / 40.69806°N 74.00556°W / 40.69806; -74.00556
System New York City Subway
Operation
Opened August 1, 1920; 96 years ago (August 1, 1920)
Closed August 2, 2013; 3 years ago (August 2, 2013) (for reconstruction)
Rebuilt September 14, 2014; 2 years ago (September 14, 2014)
Operator Metropolitan Transportation Authority
Technical
No. of tracks 2 tracks

The Montague Street Tunnel carries the N and R services of the New York City Subway under the East River between the boroughs of Manhattan and Brooklyn. The R uses the tunnel at all times, and the N also uses it during late nights.

Construction of the tunnel began on October 12, 1914, using a tunneling shield in conjunction with compressed air. The tunnel was designed by civil engineer Clifford Milburn Holland, who would later serve as the first chief engineer of the Holland Tunnel. The north tube of the tunnel was holed through on June 2, 1917, and the south tube was holed through on June 20, 1917.

It opened to revenue service on August 1, 1920, the same day as the 60th Street Tunnel, on a holiday schedule; regular service began the next day. The two new tunnels allowed passengers to make an 18-mile (29 km) trip from Coney Island, through Manhattan on the BMT Broadway Line, to Queens for a 5-cent fare. The original construction cost was $9,867,906.52, almost twice that of the 60th Street Tunnel.

On December 27, 1920, more than ten thousand passengers were forced to evacuate the tunnel. Power to the third rail was shut off after a shoe beam on a train approaching Whitehall Street fell and caused a short circuit, stranding ten subway trains inside the tunnel.

On October 29, 2012, the tunnel suffered severe flooding from Hurricane Sandy. As a result, the tunnel was closed to all train service while repairs were being made. Service in the tunnel was restored using temporary equipment on December 21. However, the MTA had announced that a complete reconstruction of the tunnel systems was needed, so the tunnel was closed for a second time on August 2, 2013. Originally slated to open by October 2014, it reopened a month early on September 14, 2014.


...