Kolkata Metro Line 6

Kolkata Metro Line 6
Kolkata KMRC logo.png
Overview
Native name কলকাতা মেট্রো লাইন ৬
कोलकाता मेट्रो लाइन ६
Type Rapid transit
System Kolkata Metro
Status Under Construction
Locale India Kolkata ,India
Termini Kavi Subhash (south)
Jai Hind (north)
Stations 24
Daily ridership 500000 (projected)
Website KMRC
Operation
Operator(s) KMRC
Character
  • Surface – 1
  • Underground – 1
  • Elevated – 21
Technical
Line length 29.10 kilometres (18.08 mi)
Number of tracks 2
Track gauge 1,435 mm (4 ft 8 12 in)
Electrification 750 V DC using third rail
Operating speed 80 km/h (designed)

Kolkata Metro Railway Line 6 Under Construction - Narkel Bagan - Rajarhat 2016-07-30 5538.JPG A connection between New Garia and the Airport (29.1 km) via E M Bypass, Saltlake and Rajarhat has started; it will help to reduce travel time between the southern fringes of Kolkata to Netaji Subhas Chandra Bose International Airport. The work on this New Garia-Airport line was inaugurated by Mamata Banerjee on 7 February 2011 with a project deadline of six years. The link between Kavi Subhas (New Garia) and the airport, to be set up at a cost of Rs4 billion, will have 24 stations with the terminal Airport station being an underground one.

Work for construction of the terminal station at New Garia for the 32-km Kavi Subhash-Airport (via Rajarhat) Metro project finally resumed on 14th February 2017 with Rail Vikas Nigam Ltd (RVNL) demarcating the plot they require for the purpose.

The 5km stretch from New Garia to Ruby Hospital is expected to start from 2018.

The stations, as declared of now, will be named after eminent personalities.


...