*** Welcome to piglix ***

Greater Gabbard wind farm

Greater Gabbard Wind Farm
2013-02 windpark.JPG
Farm seen from a plane flying from Amsterdam to London
Greater Gabbard wind farm is located in North Sea
Greater Gabbard wind farm
Location of Greater Gabbard wind farm in the North Sea
Country England
Location Inner Gabbard and The Galloper banks
North Sea
Suffolk Coast
Coordinates 51°52′48″N 1°56′24″E / 51.88000°N 1.94000°E / 51.88000; 1.94000Coordinates: 51°52′48″N 1°56′24″E / 51.88000°N 1.94000°E / 51.88000; 1.94000
Status Operational
Commission date 2012
Owner(s) Scottish and Southern
RWE Npower Renewables
Wind farm
Distance from shore 23 km (14 mi)
Power generation
Units operational 140
Make and model Siemens Wind Power: SWT3.6-107
Nameplate capacity 504 MW
2013 gross output 1.8 TWh
·

Greater Gabbard is a 504 MW wind farm on sandbanks 23 kilometres (14 mi) off the coast of Suffolk in England at a cost of £1.5 billion. Onshore construction activities commenced in early July 2008 at Sizewell. It was completed on 7 September 2012 with all of the Siemens SWT3.6-107 turbines connected.

The project was originally developed by Greater Gabbard Offshore Winds Limited (GGOWL) which was a joint venture between Airtricity and Fluor. Airtricity was subsequently bought by Scottish and Southern Energy who have bought out Fluor's 50% stake for £40m which is expected to cost £1.3b. Fluor are now contracted to design, supply, installation and commissioning of the balance of the plant. Scottish and Southern sold a 50% stake to RWE, the owners of Npower (UK), in November 2008 for £308m.

The project was given the go-ahead in May 2008 and work started in June. In July 2011 erection of the turbines was two thirds complete, with all the pile foundations installed.

In October 2009 Seajacks Ltd delivered its 7,000 tonne Leviathan vessel to Fluor Ltd which sailed to Harwich to prepare the hook-up and commissioning of an in-field substation and then installation of the turbines. The first foundations were installed in autumn 2009 with the first of a total of 140 turbines installed in the spring 2010. Electricity generation began on 29 December 2010 and construction was completed on 7 September 2012. During April 2014 to March 2015 the wind farm produced 1.7 TWh, corresponding to a capacity factor of 39%.

The wind farm may be seen by the public from the Stena Line Harwich to Hook of Holland car & passenger ferry, the route passing within a few kilometres.

An extension of the project, called Galloper, was agreed in May 2013. The proposal was to add up to 140 turbines to the development, producing up to 504 MW of electricity. The wind farm was expected to be completed in 2017. The project was being developed in partnership by RWE Innogy and SSE.


...
Wikipedia

...