*** Welcome to piglix ***

Gilgel Gibe III Dam

Gilgel Gibe III Dam
Gilgel Gibe III Dam is located in Ethiopia
Gilgel Gibe III Dam
Location of Gilgel Gibe III Dam in Ethiopia
Country Ethiopia
Location between Wolayita Zone and Dawro Zone, Southern Nations, Nationalities, and Peoples' Region
Coordinates 6°50′50″N 37°18′5″E / 6.84722°N 37.30139°E / 6.84722; 37.30139Coordinates: 6°50′50″N 37°18′5″E / 6.84722°N 37.30139°E / 6.84722; 37.30139
Purpose Power
Status Operational; power station undergoing commissioning
Construction began 2008
Opening date October 2015
Construction cost US$1.8 billion
Owner(s) Ethiopian Electric Power Corporation (EEPCo)
Dam and spillways
Type of dam Gravity, roller compacted concrete
Impounds Omo River
Height 243 m (797 ft)
Length 610 m (2,000 ft)
Spillway type Service
Spillway capacity 18,000 m3/s (640,000 cu ft/s)
Reservoir
Creates Gilgel Gibe III Reservoir
Total capacity 14.0 km3 (11,300,000 acre·ft)
Catchment area 34,150 km2 (13,190 sq mi)
Surface area 210 km2 (81 sq mi)
Power station
Commission date 2015-2016
Type Conventional
Turbines 10 x 187 MW Francis-type
Installed capacity 1,870 MW
Annual generation 6,500 GWh Est.

The Gilgel Gibe III Dam is a 243 m high roller-compacted concrete dam with an associated hydroelectric power plant on the Omo River in Ethiopia. It is located about 62 km (39 mi) west of Sodo in the Southern Nations, Nationalities, and Peoples' Region. Once fully commissioned, it will be the third largest hydroelectric plant in Africa with a power output of about 1870 Megawatt (MW), thus more than doubling total installed capacity in Ethiopia from its 2007 level of 814 MW. The Gibe III dam is part of the Gibe cascade, a series of dams including the existing Gibe I dam (184 MW) and Gibe II power station (420 MW) as well as the planned Gibe IV (1472 MW) and Gibe V (560 MW) dams. The existing dams are owned and operated by the state-owned Ethiopian Electric Power Corporation, which is also the client for the Gibe III Dam.

The US$1.8 billion project began in 2008 and began to generate electricity in October 2015. The remaining generators would be operational by 2016. The project has seen serious delays; in May 2012, full commissioning had been scheduled for June 2013. The dam was inaugurated by Prime Minister Hailemariam Desalegn on 17 December 2016.

Local and international environmental groups expect major negative environmental and social impacts of the dam and have criticized the project's environmental and social impact assessment as insufficient. Because of this and accusations that the entire approval process for the project was suspect, funding for the full construction cost has not yet been secured, as the African Development Bank has delayed a decision about a loan pending a review of the dam's environmental impact by its compliance review and mediation unit which in August 2009 accepted a call from NGOs for such a review. In August 2010 Ethiopian Prime Minister Meles Zenawi vowed to complete the dam "at any cost", saying about critics of the dam that "They don’t want to see developed Africa; they want us to remain undeveloped and backward to serve their tourists as a museum."


...
Wikipedia

...