Location of Estlink
|
|
Country | Estonia, Finland |
---|---|
General direction | south–north–south |
From | Harku converter station, Estonia 59°23′5″N 24°33′37″E / 59.38472°N 24.56028°E |
Passes through | Gulf of Finland |
To | Espoo converter station, Finland 60°12′14″N 24°33′06″E / 60.20389°N 24.55167°E |
Partners |
Elering Fingrid |
Manufacturer of conductor/cable | ABB |
Installer of conductor/cable | Global Marine Systems |
Cable layer | CS Sovereign |
Manufacturer of substations | ABB |
Installer of substations | ABB |
Construction started | 2006 |
Commissioned | 2006 |
Type | Submarine power cable |
Type of current | HVDC |
Total length | 105 km (65 mi) |
Power rating | 350 MW |
AC Voltage | 330 kV (Estonia), 400 kV (Finland) |
DC Voltage | ±150 kV |
No. of poles | 2 |
Location of Estlink 2
|
|
Country | Estonia, Finland |
---|---|
General direction | south–north–south |
From | Püssi converter station, Estonia 59°22′02″N 27°03′50″E / 59.36722°N 27.06389°E |
Passes through | Gulf of Finland |
To | Anttila converter station, Finland 60°22′36″N 25°22′01″E / 60.37667°N 25.36694°E |
Partners |
Elering Fingrid |
Manufacturer of conductor/cable | Nexans |
Installer of conductor/cable | Nexans |
Cable layer | C/S Nexans Skagerrak |
Manufacturer of substations | Siemens |
Installer of substations | Siemens |
Contractors | Empower Oy |
Expected | 2014 |
Type | subsea cable, overhead line |
Type of current | HVDC |
Total length | 171 km (106 mi) |
Power rating | 650 MW |
AC Voltage | 330 kV (Estonia), 400 kV (Finland) |
DC Voltage | 450 kV |
No. of poles | 1 |
Estlink is a set of HVDC submarine power cables between Estonia and Finland. Estlink 1 is the first interconnection between the Baltic and Nordic electricity markets following by Estlink 2 in 2014. The main purpose of the Estlink connection is to secure power supply in both regions to integrate the Baltic and Nordic energy markets.
First plans for a submarine power cable between the Baltic and the Nordic regions were proposed in 1990s. Negotiations between Eesti Energia, Pohjolan Voima, Helsingin Energia, Graninge (now E.ON Sverige), Latvenergo, Statkraft and TXE Nordic Energy, a subsidiary of TXU (now Energy Future Holdings Corporation) started In 1999, and on 9 October 2001 a contract was signed in Tallinn. However, only after the harsh winter of 2002–2003 which resulted in an increased demand for power, the project of the submarine cable between Estonia and Finland got a boost. The letter of intention for underwater sea cable was signed between Eesti Energia, Pohjolan Voima, Helsingin Energia and Latvenergo on 31 March 2003. In May 2004, the Lithuanian power company Lietuvos Energija agreed to participate in the project, shortly after which the project company AS Nordic Energy Link was established. On 29 April 2005, the Estlink project was launched. Construction of Harku converter station and land cable installation begins on 5 April 2006. The submarine cable was laid in September 2006. The Estlink cable was inaugurated on 4 December 2006 and it became fully operational on 5 January 2007.
The Estlink 1 cable was operated by AS Nordic Energy Link company, founded by Baltic and Finnish power companies. The main shareholder was Eesti Energia with 39.9% of the shares, Latvenergo and Lietuvos Energija had 25% each, and the remaining 10.1% was divided between Pohjolan Voima and Helsingin Energia (operating through their joint project company Finestlink). On 30 December 2013 the interconnector was sold to the transmission system operators Elering and Fingrid.