DEMO (DEMOnstration Power Station) is a proposed nuclear fusion power station that is intended to build upon the ITER experimental nuclear fusion reactor. The objectives of DEMO are usually understood to lie somewhere between those of ITER and a "first of a kind" commercial station. While there is no clear international consensus on exact parameters or scope, the following parameters are often used as a baseline for design studies: DEMO should produce at least 2 gigawatts of fusion power on a continuous basis, and it should produce 25 times as much power as required for breakeven. DEMO's design of 2 to 4 gigawatts of thermal output will be on the scale of a modern electric power station.
To achieve its goals, DEMO must have linear dimensions about 15% larger than ITER, and a plasma density about 30% greater than ITER. As a prototype commercial fusion reactor, DEMO could make fusion energy available by 2033. It is estimated that subsequent commercial fusion reactors could be built for about a quarter of the cost of DEMO.
The following timetable was presented at the IAEA Fusion Energy Conference in 2004 by Christopher Llewellyn Smith:
In 2012 European Fusion Development Agreement (EFDA) presented a roadmap to fusion power with a plan showing the dependencies of DEMO activities on ITER and IFMIF.
This 2012 roadmap was intended to be updated in 2015 and 2019, but EFDA was superseded by EUROfusion in 2013 and the roadmap was not further updated.
When deuterium and tritium fuse, the two nuclei come together to form a resonant state which splits to form in turn a helium nucleus (an alpha particle) and a high-energy neutron.