*** Welcome to piglix ***

Upper Kotmale Reservoir

Upper Kotmale Dam
UpperKotmaleDam-Srilanka-April2011-1.jpg
The dam under construction in April 2011.
Upper Kotmale Dam is located in Sri Lanka
Upper Kotmale Dam
Location of Upper Kotmale Dam in Sri Lanka
Official name Upper Kotmale Hydropower Project
Country Sri Lanka
Location Talawakele, Nuwara Eliya
Coordinates 06°56′48″N 80°39′29″E / 6.94667°N 80.65806°E / 6.94667; 80.65806Coordinates: 06°56′48″N 80°39′29″E / 6.94667°N 80.65806°E / 6.94667; 80.65806
Purpose O
Status Operational
Construction began 2003
Opening date 2012
Construction cost Rs. 44 billion
Owner(s) Ceylon Electricity Board
Dam and spillways
Type of dam Gravity dam
Impounds Kotmale River
Height (foundation) 35 m (115 ft)
Length 180 m (591 ft)
Width (crest) 7 m (23 ft)
Spillways 5
Spillway capacity 3,000 m3/s (105,944.0 cu ft/s)
Reservoir
Creates Upper Kotmale Reservoir
Total capacity 800,000 m3 (28,000,000 cu ft)
Surface area 250,000 m2 (2,690,978 sq ft)
Power station
Name Upper Kotmale Power Station
Coordinates 07°02′32″N 07°12′00″E / 7.04222°N 7.20000°E / 7.04222; 7.20000
Commission date July 14, 2012 (2012-07-14)
Type Run-of-the-river
Turbines 2 × 75 MW Francis-type
Installed capacity 150 MW
Annual generation 409 GWh
Website
http://www.ukhp.lk/

The Upper Kotmale Dam (also known as the Upper Kotmale Hydropower Project, or UKHP) is located in Talawakele, within the Nuwara Eliya District, in the Central Province of Sri Lanka. The dam feeds the third largest hydroelectric power station in the country.

The project was initially planned in 1968 by the local authorities, before the Government of Japan funded a study between 1985 and 1987 to further examine the hydroelectric potential in the upper reaches of Kotmale River. The feasibility study included five sites and eight alternative development schemes, and concluded with two sites which were more technically and economically feasible.

The two sites were a conventional type at Caledonia, and a run-of-the-river type at Talawakele. The project at Caledonia involved the displacement of over 2,700 families and inundation of large areas of land used for tea plantations, and thus the Caledonia site was dropped. Further funding was then provided by Japan for the engineering study, which included a review of the feasibility study, selection of an optimal development plan, development of the detailed design, and the preparation of tender documents and an environmental impact assessment report.

The environmental impact assessment report was completed in September 1994, with the final design report completed in March 1995. The environmental assessment identified key issues associated with the project, which includes impact on St. Clair's Falls aesthetics due to stream flow reductions, social impacts due to resettlement of affected people, possible effects on ground water due to tunnelling, impacts on downstream water uses due to de-watering of streams, and impacts on biodiversity. These impacts led large delays in project development.

As per the National Environmental Act of 1998, the environmental clearance was then granted to the project. The project initially faced several objections, before being officially permitted by courts of law. Construction work on the project then began in 2006, and is expected to be completed by the end of 2011.


...
Wikipedia

...