Timeboxing


In time management, timeboxing allocates a fixed time period, called a time box, to each planned activity. Several project management approaches use timeboxing. It is also used for individual use to address personal tasks in a smaller time frame. It often involves having deliverables and deadlines, which will improve the productivity of the user.

Timeboxing is used as a project planning technique. The schedule is divided into a number of separate time periods (timeboxes), with each part having its own deliverables, deadline and budget.

In project management, the triple constraints are time (sometimes schedule), cost (sometimes budget), and scope (sometimes performance).Quality is often added, sometimes replacing cost. Changing one constraint will probably impact the rest.

Without timeboxing, projects usually work to a fixed scope, such that when it is clear that some deliverables cannot be completed, either the deadline slips (to allow more time) or more people are involved (to do more in the same time). Usually both happen, delivery is late, costs go up, and often quality suffers (as per the The Mythical Man-Month principle).

With timeboxing, the deadline is fixed, but the scope may be reduced. This focuses work on the most important deliverables. For this reason, timeboxing depends on the prioritisation (with the MoSCoW method for example) of deliverables, to ensure that it is the project stakeholders who determine the important deliverables rather than software developers.

Timeboxes are used as a form of risk management, to explicitly identify uncertain task/time relationships, i.e., work that may easily extend past its deadline. Time constraints are often a primary driver in planning and should not be changed without considering project or sub-project critical paths. That is, it's usually important to meet deadlines. Risk factors for missed deadlines can include complications upstream of the project, planning errors within the project, team-related issues, or faulty execution of the plan. Upstream issues might include changes in project mission or backing/support from management. A common planning error is inadequate task breakdown, which can lead to underestimation of the time required to perform the work. Team-related issues can include trouble with inter-team communication; lack of experience or required cross-functionality; lack of commitment/drive/motivation (i.e. poor team building and management).


...