Thorpe Marsh Power Station | |
---|---|
Thorpe Marsh power station's cooling towers
|
|
Country | England |
Location | South Yorkshire, Yorkshire and the Humber |
Coordinates | 53°34′50″N 1°05′07″W / 53.580602°N 1.08534°WCoordinates: 53°34′50″N 1°05′07″W / 53.580602°N 1.08534°W |
Commission date | 1963 |
Decommission date | 1994 |
Operator(s) | Central Electricity Generating Board |
Thermal power station | |
Primary fuel | Coal |
Tertiary fuel | Heavy Fuel Oil |
Power generation | |
Nameplate capacity | 1,100 MW |
grid reference SE605097 |
Thorpe Marsh Power Station was a 1 GW coal-fired power station near Barnby Dun in South Yorkshire, England.
The station was built in 1959 and closed in 1994
In 2011 permission was given for the construction of a gas fired powerstation on the site.
Construction of the station began in 1959, it was built as a prototype for all the large modern power stations in the UK. It was commissioned between 1963 and 1965.
The plant was officially opened in 1967.
The station contained two 550 MW generating units with cross compound turbines, supplied from a single boiler. Steam was supplied at 2,300 pounds per square inch (16,000 kPa) at 1,050 °F (566 °C).
On 7 January 1973, four workmen died. A coroner's report gave a verdict of accidental death; subsequently the Factory Inspectorate began legal proceedings against the Central Electricity Generating Board (CEGB) for breaches in safety provisions.
After the privatization of the Central Electricity Generating Board (1990) the station was operated by National Power. The station closed in 1994.
The 45 acres (18 ha) site was acquired by Able UK in 1995.
During the 2007 United Kingdom floods the 400 kV substation at the site was temporarily shut down on 27 June, whilst the 275 kV substation was not affected; operational service was fully restored by early 28 June.
In October 2011, the Department of Energy and Climate Change approved the construction of a 1,500 MW combined cycle gas turbine power station at Thorpe Marsh by Thorpe Marsh Power Limited (parent Acorn Power Developments, see Acorn Energy) with an estimated cost of £984 million. Thorpe Marsh Power Limited proposed an initial capacity of 960 MW. The proposed development would also require the construction of an 11-mile (18 km) gas pipeline from Camblesforth; Thorpe Marsh Power Limited is expected to submit an application for the gas pipeline in late 2014.