*** Welcome to piglix ***

Ten Tunnels Deviation 1910, New South Wales

Ten Tunnels Deviation
Lithgow zig zag map.jpg
A 1958 map of the Lithgow Zig Zag and deviation
Overview
Line Main Western
Location Blue Mountains, New South Wales Australia
Coordinates 33°29′33″S 150°13′06″E / 33.4925858296°S 150.2184178820°E / -33.4925858296; 150.2184178820Coordinates: 33°29′33″S 150°13′06″E / 33.4925858296°S 150.2184178820°E / -33.4925858296; 150.2184178820
Start Newnes Junction station
End Zig Zag station
Operation
Work begun 1 June 1908 (1908-06-01)
Opened 16 October 1910 (1910-10-16)
Owner RailCorp
Operator NSW TrainLink
Technical
Length Ten tunnels of varying length from 70 to 825 metres (230 to 2,707 ft)
Line length 9.2 kilometres
No. of tracks 2
Track gauge 1,435 mm (4 ft 8 12 in)
Official name Great Zig Zag Railway deviation tunnels
Criteria a., c., e., f., g.
Designated 2 April 1999
Reference no. 01037

The Ten Tunnels Deviation is a 9.2 kilometre section of the Main Western railway line between Newnes Junction and Zig Zag stations in the Blue Mountains, New South Wales, Australia. The heritage listed rail deviation was constructed between 1 June 1908 and 16 October 1910 to replace the Lithgow Zig Zag, which limited the length of trains over the mountains and required two changes in direction. The deviation comprised ten tunnels of varying length from 70 to 825 metres (230 to 2,707 ft) over 3.7 kilometres. The work also included the excavation of a 61-metre (200 ft) cutting, the deepest cutting on the NSW rail system. Journey times were reduced by between 20 and 30 minutes.

The Act approving the construction of the double line deviation was passed by the New South Wales Parliament in December 1906. Construction started near the former Oakey Park Colliery on the 1 in 42 Bottom Road, which had already been duplicated in 1880. It eventually passed Bottom Points before entering a series of ten tunnels. Originally eleven were planned, but one of them was opened out instead, owing to the discovery of rock faults, leaving possibly the deepest cutting in New South Wales. The headquarters for the works was at nearby Clarence, where much of the navvies were temporarily housed. Here a temporary power station was established for rock drills, lighting, compressors, etc.

Access to the tunnel locations and the short open sections between the cliffs was extremely difficult. At one isolated point, horses and drays were placed on to the worksite by means of a crane and long jibs. There they remained until the tunnels were completed to provide them with a way out. The supply of materials for Nos. 8, 9 & 10 tunnels was expedited by the construction of a 110-metre (350 ft) funicular of the 4-rail type from near Mount Sinai on the original line. Only experienced miners were employed on the more dangerous tunnelling activities, which were carried out by day and night; with approximately 1,500 employees working each day.

The tunnels were situated on a maximum grade of 1 in 90. The line curves towards Newnes Junction after leaving the tunnels at the eastern end. Newnes Junction also had to be moved 660 metres (2,170 ft) to its current place, and two more tracks were also constructed for the Commonwealth Oil Corporation's Newnes railway line. When the deviation was completed, much of the equipment was moved to the deviation of the Lapstone Zig Zag, as well as the navvies. As a result, the population of Clarence declined rapidly. The deviation was electrified along with the rest of the line in 1957.


...
Wikipedia

...