History | |
Opened | 1 October 1978 |
Schwabstraße underground station is in Stuttgart-West district, west of the centre of the German city of Stuttgart and was at the end of the first section of the Connection line (German: Verbindungsbahn), the original underground section of the Stuttgart S-Bahn. Several lines of the S-Bahn terminate at the station. It is notable for a 1.5 km long loop at the end of the station to allow S-Bahn trains to reverse direction.
Schwabstraße station was built in the course of the construction of the Stuttgart S-Bahn in the mid-1970s. The station was built using excavation from the surface and mining techniques for the terminal loop. Its construction proved to be very difficult. The shell was completed in December 1977 and in 1978 the first section of the Connection line began operating to Schwabstraße. In 1985, line was extended to the southwest to Stuttgart University station at the University of Stuttgart.
The station is between 11 and 27 m below the street surface, lying 6 to 8 metres below the water table. It has a gradient of 1.6 per thousand. The station has an island platform with two platform edges. Platform track 1 serves trains towards Stuttgart Universität and trains terminating at Schwabstraße. Track 2 serves trains running to Stuttgart Hauptbahnhof. Access routes to the platform are at either end of the platform. At the western end of the platform the tracks to the turning loop separate from the through tracks towards Universität.
The station has an unusual operational feature, a turning loop. It runs completely underground and contains a siding for a full train. The depth of the ground covering the tunnel ranges from 17 m near the platforms to 80 m at its western end near the former Stuttgart West station. Given the number of trains using the line, a return loop was found to have a higher economic return than simple terminating tracks despite the higher construction costs.
Excavation of the loop began on 7 October 1974 and the construction of the junction structures and the first 60 m sections of the two single-track tunnel tubes of the Hasenberg Tunnels towards the Gäu Railway (Gäubahn). The actual connection to the Gäu Railway was built in 1979 and went into operation in 1985.