In industrial engineering, the standard time is the time required by an average skilled operator, working at a normal pace, to perform a specified task using a prescribed method. It includes appropriate allowances to allow the person to recover from fatigue and, where necessary, an additional allowance to cover contingent elements which may occur but have not been observed.
Standard time =normal time +allowance Where; normal time =avg time *rating factor. (take rating factor between 1.1 and 1.2)
Time times for all operations are known.
The standard time can be determined using the following techniques:
The Standard Time is the product of three factors:
The standard time can then be calculated by using: