Project Timberwind aimed to develop nuclear thermal rockets. Initial funding by the Strategic Defense Initiative ("Star Wars") from 1987 through 1991 totaled $139 million (then-year). The proposed rocket was later expanded into a larger design after the project was transferred to the Air Force Space Nuclear Thermal Propulsion (SNTP) program and underwent an audit in 1992 due to concerns raised by Steven Aftergood. This special access program provided the motivation for starting the FAS Government Secrecy project. Convicted spy Stewart Nozette was found to be on the master access list for the TIMBER WIND project.
Advances in high-temperature metals, computer modelling and nuclear engineering in general resulted in dramatically improved performance. Whereas the NERVA engine was projected to weigh about 6803 kg, the final SNTP offered just over 1/3 the thrust from an engine of only 1650 kg, while further improving the specific impulse from 930 to 1000 seconds.
In contrast to the TIMBER WIND project, the Space Nuclear Thermal Propulsion (SNTP) program was intended to develop upper-stages for space-lift which would not operate within the Earth's atmosphere. SNTP failed to achieve its objective of flight testing a nuclear thermal upper-stage, and was terminated in January 1994. The program involved coordinating efforts across the Department of Defense, the Department of Energy, and their contractors from operating sites across the U.S. A major accomplishment of the program was to coordinate Environmental Protection Agency approvals for ground testing at two possible sites.
The planned ground test facilities were estimated to cost $400M of additional funding to complete in 1992. Fewer than 50 sub-scale tests were planned over three to four years, followed by facility expansions to accommodate five to 25 1000 second full-scale tests of a 2000MW engine.
Initially, PIPET [Particle Bed Reactor Integral Performance Element Tester] was envisioned as a small, low-cost, SNTP-specific experiment for testing and qualifying PBR fuel and fuel elements. The demands by other agencies, DOE and NASA, resulted in a national test facility for NTP fuel, fuel elements, and engines. Its size out grew the SNTP Program's ability to secure the funds for such a large construction project. Though the demands were placed upon the SNTP Program to expand the facility's scope and the SNTP Program's management tried to coordinate tri-agency, DoD-DOE-NASA, support and funding, adequate funding support for the national ground test facility was not obtained.