*** Welcome to piglix ***

Piper Alpha

Piper Alpha
Piper Alpha on fire shortly after the second explosion
Date 6 July 1988 (1988-07-06)
Coordinates 58°27′35″N 0°15′04″E / 58.45972°N 0.25111°E / 58.45972; 0.25111Coordinates: 58°27′35″N 0°15′04″E / 58.45972°N 0.25111°E / 58.45972; 0.25111
Cause Explosion
Deaths 167
Property damage £1.7 billion
Inquiries Cullen Inquiry

Piper Alpha was a North Sea oil production platform operated by Occidental Petroleum (Caledonia) Ltd. The platform began production in 1976, first as an oil-only platform and later converted to add gas production. An explosion, and the resulting oil and gas fires, destroyed it on 6 July 1988, killing 167, including two crewmen of a rescue vessel; 61 survived. The total insured loss was about £1.7 billion (US$3.4 billion). At the time of the disaster, the platform accounted for approximately ten percent of North Sea oil and gas production, and the accident was the worst offshore oil disaster in terms of lives lost and industry impact.

The Kirk of St Nicholas in Union Street, Aberdeen has dedicated a chapel in memory of those who perished and there is a memorial sculpture in the Rose Garden of Hazlehead Park in Aberdeen. Thirty bodies were never recovered.

Four companies that later transformed into the OPCAL joint venture obtained an oil exploration licence in 1972, discovered the Piper oilfield located at 58°28′N 0°15′E / 58.467°N 0.250°E / 58.467; 0.250 in early 1973 and commenced fabrication of the platform, pipelines and onshore support structures. Oil production started in 1976 with about 250,000 barrels (40,000 m3) of oil per day increasing to 300,000 barrels (48,000 m3). A gas recovery module was installed by 1980. Production declined to 125,000 barrels (19,900 m3) by 1988. OPCAL built the Flotta oil terminal in the Orkney Islands to receive and process oil from the fields Piper, Claymore and Tartan, each with its own platform. One 30-inch (76 cm) diameter main oil pipeline ran 128 miles (206 km) from Piper Alpha to Flotta, with a short oil pipeline from the Claymore platform joining it some 20 miles (32 km) to the west. The Tartan field also fed oil to Claymore and then onto the main line to Flotta. Separate 18-inch (46 cm) diameter gas pipelines run from Tartan platform to the Piper, and from Piper to the gas compressing platform MCP-01 some 30 miles (48 km) to the northwest.


...
Wikipedia

...