*** Welcome to piglix ***

Ormonde Wind Farm

Ormonde Wind Farm
Vattenfall REpower 5M offshore wind turbine.jpg
Wind turbine at Ormonde Wind Farm, March 2011
Ormonde Wind Farm is located in England
Ormonde Wind Farm
Location of Ormonde Wind Farm off the coast of England
Country England, United Kingdom
Location West of Barrow-in-Furness, Irish Sea
Coordinates 54°6′N 3°24′W / 54.100°N 3.400°W / 54.100; -3.400Coordinates: 54°6′N 3°24′W / 54.100°N 3.400°W / 54.100; -3.400
Status Operational
Construction began May 2010
Commission date February 2012
Owner(s) Vattenfall
Wind farm
Type Offshore
Site area 8.7 km2 (3.4 sq mi)
Max. water depth 17–21 m (56–69 ft)
Distance from shore 9.5 km (5.9 mi)
Hub height 100 m (328 ft)
Rotor diameter 126 m (413 ft)
Power generation
Units operational 30 x 5 MW
Make and model REpower 5M
Nameplate capacity 150 MW
Annual output 500 GWh
Website
www.vattenfall.co.uk/en/ormonde.htm

The Ormonde Wind Farm is a wind farm west of Barrow-in-Furness in the Irish Sea. The wind farm covers an area of 8.7 square kilometres (3.4 sq mi). It has a total capacity of 150 MW and is expected to produce around 500 GWh of electricity per year.

Originally the Ormonde project was planned as a hybrid wind and natural gas powered electricity generation plant supplied from the Ormonde South and Ormonde North gas fields. The project was developed by Eclipse Energy. In 2008, Vattenfall bought Eclipse Energy and the project was developed as wind energy only. The project management company throughout the project has been Offshore Design Engineering.

Construction started in 2010 and was completed in August 2011.Prysmian provided submarine power cable connections including 27 km of 33 kV inter-array cables to connect the wind turbines and a 42 km of 132 kV export cable to connect the wind farm to the substation. 30 turbines each with 5 MW nameplate capacity are provided by REpower and electrical works were to be carried out by Areva. Steel foundations for generators were developed and designed by OWEC Tower and produced by Burntisland Fabrications. Logistics and assembly services are provided by Harland and Wolff. Generators were installed by A2SEA. The first four steel foundations were delivered in July 2010, and were secured to the seabed, by a procedure called structural pile grouting, by FoundOcean, the subsea and offshore grouting specialist for the global energy construction industries.

The wind farm was commissioned on 22 February 2012 and is now fully operational.


...
Wikipedia

...