Mohawk Dam | |
---|---|
Mohawk Dam aerial view
|
|
Location | Jefferson Township, Coshocton County, Ohio |
Coordinates | 40°21′06″N 82°05′18″W / 40.3518°N 82.0884°WCoordinates: 40°21′06″N 82°05′18″W / 40.3518°N 82.0884°W |
Construction began | April 1935 |
Operator(s) | United States Army Corps of Engineers, Huntington District |
Dam and spillways | |
Impounds | Walhonding River |
Height | 111 feet (34 m) |
Length | 2,330 feet (710 m) |
Reservoir | |
Total capacity | 285,000 acre feet (352,000,000 m3) |
Mohawk Dam bridge | |
---|---|
Carries | 2 lanes of SR 715 |
Mohawk Dam, located in Jefferson Township, Coshocton County, Ohio northwest of Nellie, is a dry dam constructed by the United States Army Corps of Engineers (USACE) in the mid-1930s for the purpose of flood control on the Walhonding River. The dam is part of the larger 18-county Muskingum Watershed Conservancy District (MWCD). The dam has been in service for 70 years and was recently placed on the USACE's "Urgent" dam safety classification list and plans are currently being drafted that would allocate funds for dam stabilization.
Construction of the Mohawk Dam was started in April 1935 and was completed in September 1937. The dam was authorized by the Flood Control Act of 1938 and was built as a dry dam along with 13 other dams in the Muskingum River Watershed for flood control and water conservation. The dam was built right across the right-of-way of the Walhonding Canal, which ran from Coshocton to Cavallo.
The dam has always operated as a dry dam, holding back water only during a flood and releasing it slowly downstream. The highest water level ever recorded at the Mohawk Dam was during the flood of January 2005, where the water reached a height of 80.01 feet (24.39 m) above its normal level.
The dam has been in service for 70 years but was only built with the expectation that it would function for around 50 years before sedimentation and erosion weakened the dam. The dam has weakened and several safety issues have arisen, which is why the USACE has placed it on its list of the nation's most at-risk dams, where it ranked seventh most at-risk in 2006. In 2007, the dam was classified as "Urgent", which is the second-highest classification level of the dam safety rating system used by the USACE. This classification indicates that the dam is a high federal priority for repairs since failure of the dam during a flood is moderately uncertain. The MWCD estimates that if the Mohawk Dam were to fail during a flood, the water normally held back could cost 307 people their lives and up to $449 million in property damage.