In operations research, Johnson's rule is a method of scheduling jobs in two work centers. Its primary objective is to find an optimal sequence of jobs to reduce makespan (the total amount of time it takes to complete all jobs). It also reduces the amount of idle time between the two work centers. The method minimizes the makespan in the case of two work centers. Furthermore, the method finds the shortest makespan in the case of three work centers if additional constraints are met.

The technique requires several preconditions:

Johnson's rule is as follows:

Given significant idle time at the second work center (from waiting for the job to be finished at the first work center), job splitting may be used.

Each of five jobs needs to go through work center A and B. Find the optimum sequence of jobs using Johnson's rule.

1. The smallest time is located in Job B (1.5 hours). Since the time is in Work Center B, schedule this job last. Eliminate Job B from further consideration.

2. The next smallest time is located in Job C (2.2 hours). Since the time is in Work Center A, schedule this job first. Eliminate Job C from further consideration.

3. The next smallest time after that is located in Job E (2.8 hours). Since the time is in Work Center B, schedule this job last. Eliminate Job E from further consideration.

4. The next smallest time after is located in Job A (3.2 hours). Since the time is in Work Center A, schedule this job first. Eliminate Job A from further consideration.

5. The only job left to consider is Job D.

So, the jobs must be processed in the order , and must be processed in the same order on both work centers.


...