Jatigede Dam | |
---|---|
Rendition of the future dam, downstream side on the left
|
|
Location of Jatigede Dam in Indonesia
|
|
Official name | Bendungan Jatigede |
Country | Indonesia |
Location | Sumedang, West Java |
Coordinates | 6°51′23″S 108°05′41″E / 6.85639°S 108.09472°ECoordinates: 6°51′23″S 108°05′41″E / 6.85639°S 108.09472°E |
Status | Operational |
Construction began | 2008 |
Opening date | 2015 |
Dam and spillways | |
Type of dam | Embankment, rock-fill |
Impounds | Cimanuk River |
Height | 110 m (361 ft) |
Length | 1,715 m (5,627 ft) |
Elevation at crest | 265 m (869 ft) |
Width (crest) | 110 m (361 ft) |
Dam volume | 6,700,000 m3 (8,763,269 cu yd) |
Spillway type | Chute |
Spillway capacity | 4,468 m3/s (157,786 cu ft/s) |
Reservoir | |
Total capacity | 980,000,000 m3 (794,499 acre·ft) |
Active capacity | 877,000,000 m3 (710,995 acre·ft) |
Catchment area | 1,462 km2 (564 sq mi) |
Surface area | 41.22 km2 (16 sq mi) |
Normal elevation | 260 m (853 ft) |
Power station | |
Operator(s) | Perusahaan Listrik Negara |
Commission date | 2019 (est.) |
Hydraulic head | 170 m (558 ft) (design) |
Turbines | 2 x 55 MW Francis-type |
Installed capacity | 110 MW |
The Jatigede Dam is an embankment dam on the Cimanuk River in Sumedang Regency, West Java, Indonesia. It is located 19 km (12 mi) east of the town of Sumedang. Construction on the dam began in 2008 and it was completed in 2015. The power station is expected to be commissioned in 2019. The primary purpose of the dam is irrigation but it will also provide for flood control, water supply and hydroelectric power generation. Water in the reservoir will be used to help irrigate 90,000 ha (222,395 acres) of farmland and the power station is expected to have a 110 MW capacity. The project has been become controversial, primarily due to the relocation of people in the future reservoir zone.
The dam was first proposed in 1963 after a study of the Cimanuk was carried out by Coyne et Bellier. Further planning and designs commenced thereafter. An environmental impact assessment was completed in 1986 and land acquisition study in 2003. After decades of planning and protests, the Indonesian Government announced firm plans to proceed with the dam in 2004.
The project has been surrounded with controversy over the years, particularly as its reservoir would flood 4,896 ha (12,098 acres) of land. This includes five districts and 30 villages which include approximately 70,000 people to be relocated. Affected residents claim that compensation for their land is too low and that the government intimidated them to accept offers in the 1980s. In addition, a 2011 study by Indonesia's Ministry of Public Works estimated that the reservoir would become ineffective in 50 years due to high sedimentation of the river.
Despite the controversy, the government stated in 2004 that an agreement had been reached. The contract to build the dam and power plant was awarded to China's Sinohydro Corporation in May 2007. Construction on the dam's diversion tunnel began in October 2008 and was completed in August 2011. The government announced in late 2011 that that dam was 60% complete. In July 2011, it was announced that Perusahaan Listrik Negara would oversee the construction and operation of the 110 MW power plant. The dam and power plant is expected to cost US$224 million. In May 2013 the government announced that the total cost would be around $400 million and that the dam was 70% complete. Currently, the dam was expected to start impounding its reservoir in early 2015. This major step in construction has been repeatedly delayed due to resident relocations.