Duke Energy Center | |
---|---|
General information | |
Status | Complete |
Type | Office |
Location | 550 South Tryon Street, Charlotte, NC |
Coordinates | 35°13′26.48″N 80°50′53.28″W / 35.2240222°N 80.8481333°WCoordinates: 35°13′26.48″N 80°50′53.28″W / 35.2240222°N 80.8481333°W |
Construction started | February 28, 2006 |
Opening | January 2010 |
Cost | $880 million |
Owner | Wells Fargo |
Height | |
Roof | 786 ft (240 m) |
Technical details | |
Floor count | 48 floors (54 in total with mechanical floors) |
Floor area | 1,500,000 sq ft (140,000 m2) |
Design and construction | |
Architect | tvsdesign |
Structural engineer | TRC Worldwide Engineering, Inc. |
Main contractor |
Batson-Cook Company subcontractors: Boda Plumbing, Inc.; J Davis Contracting Juba Aluminum Products Co., Inc. |
References | |
The Duke Energy Center is a 786-foot (240 m) tall, 48-floor (54 floors including mechanical floors) skyscraper in Charlotte, North Carolina. When completed in 2010, it was the largest building in Charlotte (in square footage), second tallest building in Charlotte, 63rd tallest building in the United States, and the tallest in the world to use precast double tees built by Prestress of the Carolinas. The building is named for its anchor tenant, Duke Energy, and both the tower and the adjacent cultural arts campus are owned by Wells Fargo.
Sonnenschein will use 35,000 square feet (3,300 m2) on the 34th and 35th floors and Deloitte will use 82,000 square feet (7,600 m2).
Originally, the building was to be known as the Wachovia Corporate Center. It was to replace One Wachovia Center as the headquarters of Wachovia. Wachovia was to occupy 450,000 square feet (42,000 m2) of the 1,500,000 square feet (140,000 m2) tower. Wells Fargo plans to use five of its 14 floors.
The project was announced in spring of 2004, and official renderings were not released until December 6, 2006. In the original petition to the Charlotte-Mecklenburg Planning Commission, the building was going to be built on a 1.29-acre (5,200 m2) parcel next to 400 South Tryon, with a height of 510 feet (160 m) and 34 floors. The site preparation began with the demolition of a Firestone Tire dealership in February 2006, and on February 28, 2006, the excavation and blasting of a 100-foot (30 m)-deep hole for the below-grade parking garage began. Over 600,000 pounds of explosives were used during its excavation and it took just over 60,000 dump truck loads to remove all of the excavated material from the site, some of which was used in the construction of a third runway at Charlotte-Douglas International Airport.
The building was constructed by Batson-Cook Construction, with ready mix products from Concrete Supply Co. and structural engineering firm TRC International Ltd, of Sarasota, Florida. The building core is constructed with poured-in-place concrete while the floor structures utilize precast double tees, a structural method typically seen in parking decks. These double tees span between the poured-in-place core and perimeter systems. The concrete used for the building is 18,000 pounds per square inch.