Block Island Wind Farm | |
---|---|
![]() |
|
Country | United States |
Location | New Shoreham, Rhode Island |
Coordinates | 41°06′52.96″N 71°31′16.18″W / 41.1147111°N 71.5211611°WCoordinates: 41°06′52.96″N 71°31′16.18″W / 41.1147111°N 71.5211611°W |
Status | Operational |
Construction began | 2015 |
Commission date | 12 December 2016 |
Construction cost | $290 million |
Owner(s) | Deepwater Wind |
Wind farm | |
Type | offshore |
Distance from shore | 3.8 miles (6.1 km) |
Hub height | 100 m |
Rotor diameter | 150 m |
Rated wind speed | 3–25 m/s |
Power generation | |
Units operational | 5 × 6 MW |
Make and model | Haliade 150 |
Nameplate capacity | 30 MW |
Capacity factor | 47.6% (projected) |
Planned output | 125 GW·h |
Website http://www.4coffshore.com/windfarms/block-island-wind-farm-united-states-us12.html |
Block Island Wind Farm is the first commercial offshore wind farm in the United States, located 3.8 miles (6.1 km) from Block Island, Rhode Island in the Atlantic Ocean. The five-turbine, 30 MW project was developed by Deepwater Wind. Construction began in 2015 and in late summer 2016 Alstom Haliade 150 6 MW turbines were erected. Operations were launched in December 2016. It is the largest project using wind power in Rhode Island.
A project of Deepwater Wind, Block Island Wind Farm is located about 3.3 nautical miles (6.1 km; 3.8 mi) southeast of Block Island, becoming the first offshore wind farm in the United States. The thirty-megawatt, five-turbine demonstration project is expected to produce more than 125,000 megawatt hours annually. Power is transmitted from the turbines to the electric grid, along a 21-mile (34 km) transmission submarine power cable buried under the ocean floor, making landfall north of Scarborough Beach in Narragansett. The structures, designed by Alstom Wind, stand 600 ft high (180 m) and can withstand a Category 3 storm. The system connects New Shoreham to the grid for the first time and allows it to cease using diesel generators which have been replaced with power from the cable supplying the island.Gulf Island Fabrication was interested in building the foundations.