B.P. Koirala Highway

B.P. Koirala Highway
बीपी राजमार्ग
Route information
Length: 158 km (98 mi)
Major junctions
From: Dhulikhel
To: Bardibas
Location
Primary
destinations:
Banepa, Dhulikhel, Dumja, Mangaltar, Sindhuli, Bardibas
Highway system
Roads in Nepal

The B.P. Koirala Highway, also known as the Banepa Bardibas Highway, is a highway in eastern Nepal. It links Kathmandu Valley with the Eastern Terai region. It is named after the former leader of Nepal, Bishweshwar Prasad Koirala. This highway is the shortest link between Kathmandu valley and the Terai region in Nepal. Construction of the highway began on 1996 and after encountering different issues with materials, manpower and budget, the road was finally completed and handed over to the Nepalese government on 3 July 2015.

The construction of Banepa Sindhuli Bardibas Road started in November 1996 with a grant assistance of Government of Japan. The highway was handed over by Japanese ambassador to Nepal Mr. Masashi Ogawa to the then Prime Minister of Nepal Mr. Sushil Koirala. Koirala inaugurated the highway during a ceremony held at Dhulikhel, Kavre.

The total cost of the project from start to completion was NPR. 21.5 billion (¥ 26 billion).

• Section I Bardibas- Sindhulibazar section (37 km)

• Section II Sindhulibazar- Khurkot section (39 km)

• Section III Khurkot - Nepalthok section (32 km)

• Section IV Nepalthok-Dhulikhel section (50 km)

Out of these sections, construction of Bardibas - Sindhuli Bazar section started in November 1996 and was completed in March 1998. The construction of this section included 9 bridges and 17 causeways over the 37 km of road, which was constructed in 1987. This section has been opened to traffic since its completion in 1998.

The construction of Nepalthok-Dhulikhel section started in April 1998 and is under construction. This section includes construction of 50 km of road with 5 bridges and 6 causeways. Out of 50 km, 34 km has been completed and is already open to public traffic while rest of the road was expected to be complete by March 2003.

The construction of Sindhulibazar-Khurkot section was slated to start in January 2001, this section includes construction of 39 km of road with a bridge and 3 causeways. Earthwork over 12.5 km of this road section was completed in the previous phase. This section was expected to be complete by 2007.

After the promulgation of Environmental Protection Act (EPA) for the first time during the basic design of section II Sindhulibazar Khurkot section, a Complete Environmental Impact Assessment was conducted. Extensive discussion on various aspects on environmental issues was discussed with the local people and their concerns are properly addressed. Furthermore, various slope stabilization techniques has been adopted, this includes use of retaining and breast walls, crib works, gabion works, geotextiles and most interesting being the bio-engineering works which includes the locally available techniques like plantation of trees, shrubs including turfing and the soil seeding method imported from Japan. Though initially this technique has been found little expensive because most of the materials used in this method being imported from Japan and for making this method economical effort has been made to use the locally available materials so that this method could be extensively used in Nepal.


...