Almatti Dam

Almatti dam
ಆಲಮಟ್ಟಿ ಅಣೆಕಟ್ಟು
Alamatti dam.JPG
Almatti Dam with its right bank power house
Official name Upper Krishna-I (Almatti)
Location Vijaypur district, Karnataka - Basavana Bagewadi Taluk, North Karnataka
Coordinates 16°19′52″N 75°53′17″E / 16.331°N 75.888°E / 16.331; 75.888Coordinates: 16°19′52″N 75°53′17″E / 16.331°N 75.888°E / 16.331; 75.888
Opening date July 2005
Construction cost Rs. 5.20 billion
Operator(s) Karnataka Power Corporation Limited
Dam and spillways
Impounds Krishna River
Height 52.25 m
Length 1565.15 m
Reservoir
Total capacity 123.08 Tmcft at 519 m MSL
Catchment area 33,375 sq. km
Surface area 24,230 hectares
Minimum Draw Down Level : 504.75 m MSL

The Almatti Dam (Kannada:ಆಲಮಟ್ಟಿ ಅಣೆಕಟ್ಟು) is a hydroelectric project on the Krishna River in North Karnataka, India which was completed in July 2005. The target annual electric output of the dam is 560 MU (or GWh).

The Almatti Dam is the main reservoir of the Upper Krishna Irrigation Project; the 290 MW power station is located on the right side of the Almatti Dam. The facility uses vertical kaplan turbines: five 55MW generators and one 15MW generator. Water is released in to the Narayanpur reservoir after using for power generation to serve the downstream irrigation needs.

During the initial stages of the project, estimated costs were projected as Rs.14.70 billion, but following the transfer of project's management to the Karnataka Power Corporation Limited (KPCL), the estimated cost was reduced by over fifty percent to Rs. 6.74 billion. The KPCL eventually completed the project at an even lower cost of Rs. 5.20 billion. The entire dam was finished in less than forty months, with construction ending in July 2005. The dam is located on the edge of Bijapur and Bagalkot districts. Geographically, it is located in the Bijapur district, but large areas of Bagalkot district have also been submerged due to filling of the reservoir. The dam holds a gross water storage capacity of 123.08 TMC at 519 meters MSL.

The full reservoir level of Almatti dam was originally restricted to 519 meters MSL by the supreme court of India.The Krishna River conflict between Andhra Pradesh, Karnataka, and Maharashtra was resolved by the Brijesh Kumar Tribunal and the dam was authorised to be raised to the height of 524 meters MSL with nearly 200 TMC gross storage capacity.


...