Access to the Region's Core

ARC Tunnel
Overview
Location Hudson Palisades/Hudson River
Coordinates 40°45′17″N 74°01′00″W / 40.75479°N 74.01677°W / 40.75479; -74.01677Coordinates: 40°45′17″N 74°01′00″W / 40.75479°N 74.01677°W / 40.75479; -74.01677
Status Canceled as of October 2010
System New Jersey Transit
Start North Bergen, New Jersey
End New York City
Operation
Work begun June 2009
Operator New Jersey Transit
Traffic Train
Character Passenger
Technical
No. of tracks 2 single-track tubes
Track gauge 1,435 mm (4 ft 8 12 in) standard gauge
Electrified 12 kV overhead catenary
Lowest elevation 100 ft (30.5 m) below river level
Tunnel clearance 24.5 ft (7.5 m)
Grade 0.3 – 0.8%

Access to the Region's Core (ARC) was a commuter rail project to increase passenger service capacity on New Jersey Transit (NJT) between Secaucus Junction in New Jersey and Manhattan in New York City. New infrastructure would have included new trackage, a new rail yard, and a tunnel under the Hudson River. A new station adjacent to New York Penn Station was to be constructed as running more trains into the current station was deemed unfeasible. An estimated budget for the project was $8.7 billion. Construction began in mid-2009 and the project was slated for completion in 2018, but it was cancelled in October 2010 by Governor Chris Christie, citing the possibility of cost overruns and the state's lack of funds. $600 million had been spent on the project.

The project was initiated after studies conducted in the 1990s determined that new rail tunnels under the Hudson River were the best approach to address transportation needs for the New York metropolitan area. At times called the Trans Hudson Express Tunnel (THE Tunnel) or the Mass Transit Tunnel, it eventually became known by the name of a Major Investment Study, and received endorsements from both New Jersey and New York governors. It was colloquially dubbed the tunnel to Macy's basement, in reference to its terminus under 34th Street (Manhattan).

After its cancellation, the federal government demanded repayment of funding received by NJT for the project. The Christie administration engaged a law firm to present its arguments for non-payment, which were subsequently rejected by the Federal Transit Administration. An agreement was eventually reached in which part of the funds would be returned while other monies would be used on transit-related projects.

Soon after work was halted, there was speculation that the previously discussed idea of New York Transit Authority's 7 Subway Extension continuing into New Jersey would be revived, but was later scuttled. In February 2011, Amtrak announced the Gateway Project, a plan to build a right of way and new tunnels from Newark Penn Station to New York Penn Station, passing through Secaucus Junction, which would be shared with NJT trains.


...